Projetu PNDS Siklu 6 tinan 2024 Konstrusaun Aula Merenda Escolar husi Setore Educasaun no Desporto Munisipiu Lautem Suku Cotamutu Fatin Projetu Boanomara nebe implementa husi Kompanha AFABUBO FURAK, UNIPESSOAL.LDA hahu konstrui iha Fulan JULLU 2024 remata fulan OUTUBRU 2024, alokasaun orsamentu USD 48,500.00 Kontratu USD 48,500.00 gastus USD48,215.80 no balansu USD 284.20 nia progresu fiziku 100% no finalizadu ona.