Projetu PNDS Siklu 6 tinan 2024 Rehabilitasaun Estrada ( Estrada Betaun )husi Dalan, Ponte no Kontrola de Cheias,Munisipiu Lautem Suku Euquisi Fatin Projetu Barliu nebe implementa husi Kompanha HUPAI , UNIPESSOAL.LDA hahu konstrui iha Fulan JULLU 2024 remata fulan OUTUBRU 2024, alokasaun orsamentu USD 44,470.21no kontratu USD 44,470.21 gastus USD 44,348.50 no balansu USD $ 121.71 nia progresu fiziku 100% no finalizadu ona.