Rehabilitasaun Sala Escola Pre-Primaria

  • Owner: PNDS Munisipiu Lautem
  • Location: Motara, Suku Bauro
  • Date: [07/2023 - 10/2023 ]
  • Budget: $46,232.06
  • Status: FINISH

Projetu PNDS Siklu 5 tinan 2023  Rehabilitasaun Sala Escola Pre-Primaria, husi Setore Educasaun no Desporto Munisipiu Lautem Suku Fuiloro Fatin Projetu Titilari nebe implementa husi  Kompanha FENI ALFANYO ,UNIP.LDA hahu konstrui iha Fulan JULLU 2023 remata fulan OUTUBRU 2023, alokasaun orsamentu USD 46,232.06no kontratu USD   46,232.06 gastus USD46,181.95 no balansu  USD 50.11 nia progresu fiziku 100% no finalizadu ona.